Grader Teams update - 5th June

Published on 05 June 2025

Grader Teams Update (10).png

Our weekly update to residents regarding the ongoing work being carried out on our extensive road network by our grader teams is back for another week.

Don't forget to let us know if you see a road issue!  You can report an issue by using the 'Snap Send Solve' app (available for iOS and Android), via www.yarriambiack.vic.gov.au, or by calling Customer Service on #03 5398 0100.

Northern Grader Teams

1️⃣ P126 - Maintenance grading completed on Centre Hill Road and Hollands Road. Maintenance grading has now begun on Turriff West Road.

2️⃣ P121 - Gravel shoulder resheet works are ongoing on Rosebery Rainbow Road.

3️⃣ P122 - Maintenance grade completed on Yaapeet South Road. Maintenance grading has begun on the Hopetoun-Yaapeet Road.

Central Grader Teams

4️⃣ P120 - Grading works continue on Keam Road.

5️⃣ P123 -A resheet of Browns Lane has commenced.

6️⃣ P124 - Grading works continue on Keam Road.

Southern Grader Teams

7️⃣ P125 & 8️⃣ P127 - Combined teams have completed grading works on Crams Road and Staricks Road. Grading works began on Lierschs Pit Road, North East Road, and Teppers Road this week.

 