Grader Teams Update 3rd October

Published on 03 October 2025

Grader Teams Update (1).png

Our weekly update to residents regarding the ongoing work being carried out on our extensive road network by our grader teams is back for another week.

Don't forget to let us know if you see a road issue!  You can report an issue by using the 'Snap Send Solve' app (available for iOS and Android), via www.yarriambiack.vic.gov.au, or by calling Customer Service on 03 5398 0100.

Northern Grader Teams

1️⃣ P126 - Completed maintenance works on Nandaly-tempy Road.

2️⃣ P121 - Has now completed shoulder resheet works on Lascelles West Road. A shoulder resheet is now underway on the Goyura East school bus route.

3️⃣ P122 - Resheet works on Yaapeet North Road are continuing.

Central Grader Teams

4️⃣ P123 - The resheet of Areegra Exchange Road has been completed. This included an 800 metre section that was stabilised to improve performance in wet conditions. Works are now underway on the Donald-Boolite Road resheet.

5️⃣ P120 - Grading works have been carried out of Sleep's Lane and Clyne Roa

Image-81.jpg

d.

6️⃣ P124 - Currently awaiting maintenance servicing.

Southern Grader Teams

7️⃣ P125 & 8️⃣P127 - Completed grading works on Coorong Swamp Road, Murtoa Cemetery Road, and Teppers Road this week.

 

Image-83.jpg
Image-79.jpg
Image-80.jpg
Image-82.jpg
Image-83.jpg