Northern Grader Teams
P126 - Completed grading works on Kellys Road, Barbary Road, Pearce And Barbary Road, and Binders Road.
P121 - Completed grading works on Warren Road. Continuing grading works on Molyneaux Road.
P122 - Out-of-service (repairs).
Central Grader Teams
P120 - Commenced resheeting works on Mellis Road.
P123 - Completed shoulder works on Sheep Hills-Kellalac Road. Currently out-of-service (maintenance).
P124 - Assisting the Southern Grader Teams.
Southern Grader Teams
P125 - Completed grading works on Dalcross Road and Morgans Road.
P127 - Completed grading works on Webbs Dry Weather Road, Gavans Road, Konigs Road, and Forest Home Road. Commenced grading works on Delahuntys Road.