Northern Grader Teams
P126 - Out-of-service (staffing).
P121 - Completed grading works on Beyal North Road and Addinsall Road. Commenced grading works on Appledores Road.
P122 - Completed grading works and commenced resheeting works on the east section of Rosebery-Rainbow Road. Commenced gravel grading works on Boundary Road.
Central Grader Teams
P120 - Out-of-service (undergoing repairs).
P123 &
P124 - Combined teams have completed shoulder works on Sheep Hills-Kellalac Road. Commenced shoulder works on Brim East Road.
Southern Grader Teams
P125 &
P127 - Combined teams have commenced full road rehabilitation works on Banyena-Pimpinio Road, starting at the Stawell-Warracknabeal Road intersection, heading West 2700m.