Published on 15 August 2025
Our weekly update to residents regarding the ongoing work being carried out on our extensive road network by our grader teams is back for another week.
Don't forget to let us know if you see a road issue! You can report an issue by using the 'Snap Send Solve' app (available for iOS and Android), via www.yarriambiack.vic.gov.au, or by calling Customer Service on #03 5398 0100.
P126 - Completed resheeting works (2kms) on Turriff West Road and Yarto Speed Road.
P121 - Completed grading works on Prices Road. Commenced grading works on Maidavale Road and Hiltons Road.
P122 - Out-of-Service (maintenance).
P120 - Out-of-Service (inclement weather), commenced sign maintenance works.
P123 - Out-of-Service (maintenance), commenced sign maintenance works.
P124 - Out-of-Service (inclement weather), commenced grading works on Lawler Road (when weather allows).
P125 & P127 - Combined teams have completed grading works on 3LK Road.