Grader Teams Update 13 February 2026

Published on 13 February 2026

Grader Teams Update - tile (1).png

Our weekly update to residents regarding the ongoing work being carried out on our extensive road network by our grader teams is back for another week.

Don't forget to let us know if you see a road issue!  You can report an issue by using the 'Snap Send Solve' app (available for iOS and Android), via www.yarriambiack.vic.gov.au, or by calling Customer Service on #03 5398 0100.

Northern Grader Teams

1️⃣ P126 - Out-of-service (maintenance).

2️⃣ P121 - Completed shoulder works on Galaquil East Road.

3️⃣ P122 - Completed grading works on the west section of Rosebery-Rainbow Road and McFarlanes Road.

Central Grader Teams

4️⃣ P120 - Commenced maintenance grading works on Wilkur South School Road.

5️⃣ P123 & 6️⃣ P124 - Combined teams have commenced maintenance grading works on Brikkle Road.

Southern Grader Teams

7️⃣ P125 & 8️⃣ P127 - Combined teams continuing full road rehabilitation construction works on Banyena-Pimpinio Road.