Grader Teams Update 11th September

Published on 11 September 2025

Grader Teams Update (1).png

Our weekly update to residents regarding the ongoing work being carried out on our extensive road network by our grader teams is back for another week.

Don't forget to let us know if you see a road issue!  You can report an issue by using the 'Snap Send Solve' app (available for iOS and Android), via www.yarriambiack.vic.gov.au, or by calling Customer Service on #03 5398 0100.

Northern Grader Teams

1️⃣ P126 - Currently working on the Tempy East Road resheet. Grading works are also being undertaken while in the area on Nandaly Tempy Road and Tempy East Road.

2️⃣ P121 - Gravel patch-ups have been completed on Mills and Ferguson Roads.

3️⃣ P122 - Grading works on Anderson Neville Road, and Jolly's Road. Works are nearly completed on Nyallo Road.

Central Grader Teams

4️⃣ P123 has completed grading Ellam Willenabrina Road and is now on Brina North Road.

5️⃣ P120 - Out-of-Service (maintenance)

6️⃣ P124 ismaintenance grading Areegra Exchange Road in preparation for a 1200m re-sheet.

 

Southern Grader Teams

7️⃣ P125 and 8️⃣ P127 have graded Dyers Estate Rd, Morgan’s Rd and are now grading Starbucks Road

 

 